Progressive Renovation
Scripture teaches progressive sanctification; we do not become perfectly righteous as Christ is righteous when we first become Christians. We instantly go from dead to alive, but perfection comes slowly. The same is true of our building: we practice progressive renovation. The body of Christ is slowly building this temple of worship. This means volunteers are dedicating love and care alongside small children after work hours and on weekends. The progress may seem slow, but it is an investment in our children’s children and the kingdom of God. Thank you for forbearing with our renovations as we grow into this wonderful new building which God has blessed us with. We thank God for what he has given us, and we work to make it better.
Scroll down for our project priorities, workday information, and photo updates.
Project Priorities (Milestone Goal):
Phase 1
#1 Open the Kids Wing for CTK|Kids (March 2) Delayed until 3/9?
#2 Improve Main Entrance and Lounge (March 23)
#3 Settle Interior Design and Visitor Experience (April 13)
#4 Hard Launch (April 20)
Phase 2
#1 Improve Sanctuary Tech and Experience
#2 Exterior Repairs
#3 Public Access
Workdays:
Please click on the date below to register for a workday. This helps us prepare materials and tasks for you to effectively work. The harvest is plentiful, but the laborers are few!
Currently Scheduled Workdays:
3/15, Saturday (9-5): Moving Day
Project Updates:
February 22
Monitors installed in Nursing Mothers Room and Sanctuary Hallway for parents to hear the sermon while caring for their kids. Kids Hallway painted.
February 18
Kids Hallway was painted the first coat of its new color, interior cameras installed on first floor, and waste removed. Michael’s office prepped for painting.